During September and October 2018, the site compound set-up and mobilisation of plant was completed. Dredging operations commenced with the berthing pocket and main navigation channel and sampling and testing of dredged material was also carried out.  By the end of 2018, the total material dredged /excavated amounted to 28,812m3.

Installation of the sheet piles commenced in November, with almost 60m of sheet pile wall installed by the end of 2018.

A marine archaeologist and marine mammal observer are assigned to the project for environmental monitoring during dredging and piling operations.  Three buoys have been deployed near the site for monitoring purposes, in particular to monitor turbidity in the water.

 

Drone footage (January 2019)

Added 21.03.2019

Site Compound Set up (Sept 2018)

Added 21.03.2019

Commencement of Works (Sept 2018)

Added 21.03.2019

Construction in Progress (Nov 2018)

Added 21.03.2019

Sheet piles on the northern end of the new pier (January 2019)

Added 21.03.2019

Dredging Works (January 2019)

Added 21.03.2019